據(ju)CSPPLAZA平(ping)臺(tai)會員單位——甘肅安裝建(jian)設集(ji)團有(you)限公(gong)司(簡稱(cheng):甘肅安裝集(ji)團)消息(xi),8月(yue)22日,新華發電(dian)博州10萬千瓦(wa)儲熱(re)(re)型光熱(re)(re)項目主(zhu)廠房汽輪機基座大體積混凝土順利(li)澆筑(zhu)。
主廠房汽輪發電機基礎位于主廠房5軸-8軸/A軸-B軸之間(jian)位置,基礎混凝土厚度為2m,澆筑(zhu)方量(liang)為430m3,屬于大體積混凝土。項目部(bu)合理安(an)(an)排澆筑(zhu)計劃,優化施工(gong)方案明(ming)確任務目標,精心(xin)組織各工(gong)作面(mian)的(de)施工(gong),加強過程(cheng)管(guan)控,克服高溫炎(yan)熱天氣等困難,力保(bao)現場施工(gong)安(an)(an)全質量(liang)的(de)同時,更在(zai)保(bao)障施工(gong)安(an)(an)全的(de)前提下,確保(bao)了高標準的(de)工(gong)程(cheng)質量(liang)。
主廠房汽輪機基座大體積混(hun)凝(ning)土澆(jiao)筑(zhu)是(shi)光熱項目一個重要施(shi)工(gong)(gong)(gong)(gong)節(jie)點,為后(hou)續設備進場安裝工(gong)(gong)(gong)(gong)作創造了(le)工(gong)(gong)(gong)(gong)作面,為項目的早(zao)日竣工(gong)(gong)(gong)(gong)和投產創造了(le)有利條件。接(jie)下來(lai)項目部將持續加強(qiang)項目管理,確保施(shi)工(gong)(gong)(gong)(gong)質(zhi)量(liang)和安全,同(tong)時不斷(duan)優化施(shi)工(gong)(gong)(gong)(gong)流程,積極加強(qiang)技術(shu)創新,提高施(shi)工(gong)(gong)(gong)(gong)效率和管理水平,全力以赴確保工(gong)(gong)(gong)(gong)程按期竣工(gong)(gong)(gong)(gong)。