8月18日,三峽恒基能脈瓜州70萬千瓦“光熱儲能+”項目330kV橋灣匯集升壓站及送出線路工程順利開工。
此(ci)次開工建設的橋灣(wan)匯集升壓站主變總容(rong)量1200MVA,送(song)出(chu)線路長度約35km,可同時(shi)滿(man)足三峽恒(heng)基(ji)能(neng)脈瓜州70萬(wan)千瓦“光熱儲能(neng)+”項目(mu)(mu)、浙江運達150MW風電(dian)項目(mu)(mu)、東方電(dian)氣100MW風電(dian)項目(mu)(mu)、華銳100MW風電(dian)項目(mu)(mu)的接入需求。
該工程(cheng)由三峽恒基能脈(酒泉)新(xin)能源發電有限公司牽頭組織建設(she),計劃2022年底建成(cheng)投(tou)產。
據CSPPLAZA此前(qian)報道(dao),三(san)峽恒基能(neng)脈(mo)瓜(gua)州“10萬(wan)(wan)千(qian)(qian)瓦(wa)光(guang)熱+20萬(wan)(wan)千(qian)(qian)瓦(wa)光(guang)伏(fu)+40萬(wan)(wan)千(qian)(qian)瓦(wa)風(feng)(feng)電(dian)(dian)”項目是甘肅省第(di)一批大型(xing)風(feng)(feng)電(dian)(dian)光(guang)伏(fu)基地建設項目,是2021年10月酒泉市集(ji)中(zhong)開工新能(neng)源項目。項目總裝機(ji)容量(liang)70萬(wan)(wan)千(qian)(qian)瓦(wa),其(qi)中(zhong):光(guang)熱發(fa)電(dian)(dian)裝機(ji)10萬(wan)(wan)千(qian)(qian)瓦(wa),光(guang)伏(fu)發(fa)電(dian)(dian)裝機(ji)20萬(wan)(wan)千(qian)(qian)瓦(wa),風(feng)(feng)力發(fa)電(dian)(dian)裝機(ji)40萬(wan)(wan)千(qian)(qian)瓦(wa)。
光熱發電采(cai)用塔(ta)式(shi)熔鹽(yan)技(ji)術路(lu)線,裝(zhuang)機(ji)(ji)規模為2×50MW,雙塔(ta)一機(ji)(ji)模式(shi),配套兩(liang)座吸熱塔(ta)、一臺超高壓、一次中間(jian)再(zai)熱、8級回熱(暫定)、軸向排汽(qi)、直(zhi)接(jie)空(kong)冷凝(ning)汽(qi)式(shi)汽(qi)輪(lun)機(ji)(ji),汽(qi)輪(lun)機(ji)(ji)額(e)定容(rong)量為1×100MW。
據了解,目前三峽恒基能(neng)脈(酒泉)新能(neng)源發電有限公司由姚志豪博士擔(dan)任法人(ren)代(dai)表兼(jian)董事長,由恒基能(neng)脈新能(neng)源科技有限公司控股51%,中國三峽新能(neng)源(集團(tuan))股份有限公司持股49%。