12月13至14日,新(xin)疆電力工程質(zhi)量監督中心站專家組(zu)(zu)一行5人(ren)對哈密光(guang)熱項目機(ji)組(zu)(zu)進行建筑(zhu)工程交(jiao)付(fu)使用(yong)前及機(ji)組(zu)(zu)整套啟動試運前質(zhi)量監督檢查。
專家組對各專業(ye)進(jin)(jin)行(xing)對口檢查,對工(gong)(gong)程(cheng)的質(zhi)(zhi)(zhi)量(liang)(liang)行(xing)為、“強制性條文”的執(zhi)行(xing)情(qing)(qing)況和工(gong)(gong)程(cheng)實體(ti)質(zhi)(zhi)(zhi)量(liang)(liang)及(ji)技術文件、資料進(jin)(jin)行(xing)了(le)重(zhong)點檢查和抽查。首次會上(shang),項目(mu)部(bu)從工(gong)(gong)程(cheng)概況與(yu)特點、主要施(shi)工(gong)(gong)范圍與(yu)工(gong)(gong)期(qi)節點、質(zhi)(zhi)(zhi)量(liang)(liang)管理體(ti)系及(ji)其運行(xing)效果、施(shi)工(gong)(gong)質(zhi)(zhi)(zhi)量(liang)(liang)目(mu)標、工(gong)(gong)程(cheng)實體(ti)質(zhi)(zhi)(zhi)量(liang)(liang)驗收情(qing)(qing)況、安(an)(an)裝及(ji)調試過程(cheng)中(zhong)發現的主要設備質(zhi)(zhi)(zhi)量(liang)(liang)和處理結果,工(gong)(gong)程(cheng)安(an)(an)全文明施(shi)工(gong)(gong)管理情(qing)(qing)況等8個方(fang)面,全面介(jie)紹了(le)儲換熱熔鹽系統與(yu)蒸汽(qi)系統的相(xiang)關狀況。
在施工現場檢查(cha)和資料審查(cha)中,專家(jia)組(zu)通過對(dui)儲換(huan)熱區(qu)進行全(quan)面的檢查(cha),專家(jia)組(zu)認為(wei)儲換(huan)熱區(qu)已按設計基本完成施工,質(zhi)量管理體系健(jian)全(quan),主要質(zhi)量管理程序履行到位,生產(chan)準備工作已基本就緒(xu)。尾工和整改項目驗(yan)收合格(ge)后,可進入(ru)整套啟動試運。
注:文章轉載自中國能建安徽電建一公司。